FABRICATION WORK CARRIED OUT AT UMBRAHAT FOR 42” SBHT PIPELINE PROJECT
PROJECT NAME : |
FABRICATION WORK CARRIED OUT AT UMBRAHAT FOR 42″ SBHT PIPELINE PROJECT |
YEAR : |
2016 |
LOCATION : |
NAVSARI, GUJRAT INDIA |
OPERATOR : |
M/S. ONGC LTD. |
CLIENT : |
M/S. LARSEN & TOUBRO LTD. |
VALUE (M. INR) : |
23.6 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
FABRICATION OF STRUCTURAL MEMBERS, HANDRAILS, GRATING, WORKING PLATFORMS, SADDLE SUPPORTS ETC |
MHNRD-III HOOK-UP & MODIFICATION WORKS UNDER MHNRD-III – 5 WELL PLATFORM PROJECT
PROJECT NAME : |
MHNRD-III HOOK-UP & MODIFICATION WORKS UNDER MHNRD-III – 5 WELL PLATFORM PROJECT |
YEAR : |
2015 |
LOCATION : |
MUMBAI HIGH NORTH FIELD , INDIA |
OPERATOR : |
M/S. ONGC LTD. |
CLIENT : |
M/S. LARSEN & TOUBRO LTD. |
VALUE (M. INR) : |
69.5 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
HOOK-UP AND PRECOMMISSIONING WORKS ON WELL PLATFORMS N-19, N-21, N-22 & N-24 AND MODIFICATION ON MNW PROCESS( DO TOWER) AND N-11 WELL PLATFORM( CLAMPON RELATED MODIFICATION) |
FABRICATION OF N-19 DECK INCLUDING E&I, PIPING & ARCHITECTURAL WORKS FOR MHNRD-III WELL HEAD PROJECT
PROJECT NAME : |
FABRICATION OF N-19 DECK INCLUDING E&I, PIPING & ARCHITECTURAL WORKS FOR MHNRD-III WELL HEAD PROJECT |
YEAR : |
2015 |
LOCATION : |
HAZIRA, GUJRAT. INDIA |
OPERATOR : |
M/S. ONGC LTD. |
CLIENT : |
M/S. LARSEN & TOUBRO LTD. |
VALUE (M. INR) : |
83 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
FABRICATION OF N-19 WELL PLATFORM DECK STRUCTURE INCLUDING PIPING, E&I AND ARCHITECTURAL AT LTHE HAZIRA YARD. |
CLEARANCE OF ICPR PUNCH POINTS
PROJECT NAME : |
CLEARANCE OF ICPR PUNCH POINTS |
YEAR : |
2015 |
LOCATION : |
MUMBAI HIGH SOUTH FIELD, INDIA |
OPERATOR : |
M/S. ONGC LTD. |
CLIENT : |
M/S. AFCONS – GUNANUSA JOINT VENTURE |
VALUE (M. INR) : |
22.5 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
PUNCH POINT RELATED WORKS FOR EQUIPMENT, E&I, PIPING ETC PERTAINING TO ICPR PROCESS PLATFORM. |
UPGRADATION OF SILOS & ALLIED EQUIPMENTS OF BULK HANDLING PLANT (BHP), NHAVA
PROJECT NAME : |
UPGRADATION OF SILOS & ALLIED EQUIPMENTS OF BULK HANDLING PLANT (BHP), NHAVA |
YEAR : |
2015 |
LOCATION : |
NHAVA ONGC, MAHARASHTRA |
OPERATOR : |
M/S. ONGC LTD. |
CLIENT : |
M/S. ONGC LTD. |
VALUE (M. INR) : |
92.58 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
DESIGN, ENGINEERING, PROCUREMENT, INSTALLATION OF 8 NOS SILOS AND ALLIED EQUIPMENTS OF BULK HANDLING UNIT AT ONGC NHAVA. |
E&I WORK FOR VSEB & VSEC OF ADVEP PROJECT
PROJECT NAME : |
E&I WORK FOR VSEB & VSEC OF ADVEP PROJECT |
YEAR : |
2015 |
LOCATION : |
HAZIRA, GUJRAT. INDIA |
OPERATOR : |
M/S. ONGC LTD. |
CLIENT : |
M/S. LARSEN & TOUBRO LTD. |
VALUE (M. INR) : |
11.2 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
ELECTRICAL & INSTRUMENTATION WORK SUCH AS INSTALLATION OF CABLE TRAY, CABLE, INSTRUMENTS, INSTRUMENT TUBING, SHUTDOWN PANEL, CALIBRATION AND TESTING OF INSTRUMENTS ETC. |
ADVEP PROJECT - ADDITIONAL DEVELOPMENT OF VASAI EAST PROJECT
PROJECT NAME : |
ADVEP PROJECT – ADDITIONAL DEVELOPMENT OF VASAI EAST PROJECT |
YEAR : |
2015 |
LOCATION : |
MUMBAI HIGH, BASSEIN FIELD, INDIA |
OPERATOR : |
M/S. ONGC LTD. |
CLIENT : |
M/S. LARSEN & TOUBRO LTD. |
VALUE (M. INR) : |
69.5 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
HOOK UP & COMMISSINING WORK OF NEW WELL PLATFORMS VSEB & VSEC AND RELATED MODIFICATION OF EXISTING BPA PROCESS COMPLEX WHICH INCLUDES INSTALLATION OF 3 PHASE HP SEPARATOR, MOL PUMP, STP, NEW GAS RECIVER, PIPING (APPROX 6400 INCH DIA), STRUCTURAL ( 200 MT) AND E&I WORKS. |
FABRICATION, TRANSPORTATION , ERECTION & HOOK UP OF FLOW ARMS AT DDW1 OFFSHORE PLATFORM FOR KG-OSN-2001/3 BLOCK
PROJECT NAME : |
FABRICATION, TRANSPORTATION, ERECTION & HOOK UP OF FLOW ARMS AT DDW1 OFFSHORE PLATFORM FOR KG-OSN-2001/3 BLOCK |
YEAR : |
2015 |
LOCATION : |
K .G BASIN ,DEEN DAYAL FIELD. EAST COAST OF INDIA |
OPERATOR : |
M/S. GSPC LTD. |
CLIENT : |
M/S. GSPC LTD. |
VALUE (M. INR) : |
66.8 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
FABRICATION ,INSTALLATION AND HOOK-UP OF 11 NOS DSS FLOWARMS(36 MM THK) ON DDW1 WELL PLATFORM. |
YETAGUN NORTH DEVELOPMENT PROJECT , MYANMAR
PROJECT NAME : |
YETAGUN NORTH DEVELOPMENT PROJECT , MYANMAR |
YEAR : |
2014 |
LOCATION : |
MARTBAN GULF, MYANMAR |
OPERATOR : |
PC MYANMAR (HONG KONG) LIMITED |
CLIENT : |
M/S. LARSEN & TOUBRO LTD. |
VALUE (M. INR) : |
185 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
HOOK -UP AND PRECOMMISSIONG OF WELL PLATFORM YET-D AND REATED MODIFICATION ON EXISTING PLATFORM YET-C AT MYANMAR |
E&I WORK FOR GTG & GDU (MODULE 2)AND PGC (MODULE 1) OF SAGAR PRAGATI
PROJECT NAME : |
E&I WORK FOR GTG & GDU (MODULE 2)AND PGC (MODULE 1) OF SAGAR PRAGATI |
YEAR : |
2014 |
LOCATION : |
HAZIRA ,GUJRAT. INDIA |
OPERATOR : |
M/S. ONGC LTD. |
CLIENT : |
M/S. LARSEN & TOUBRO LTD. |
VALUE (M. INR) : |
15.5 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
ELECTRICAL AND INSTRUMENTATION WORKS RELATED TO PGC 1& 2 |
B-127 & HRP –II PROJECT
PROJECT NAME : |
B-127 & HRP –II PROJECT |
YEAR : |
2013 |
LOCATION : |
MUMBAI HIGH HEERA & BASSEIN FIELD, INDIA |
OPERATOR : |
M/S. ONGC LTD. |
CLIENT : |
M/S. LARSEN & TOUBRO LTD. |
VALUE (M. INR) : |
640 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
HOOK-UP AND PRE-COMMISSIONING OF 7 WELL PLATFORMS (B-127, B-157, B55-5, ZC, HK, HSD & HP) IN MUMBAI HIGH |
GSPC PLQP PROJECT OFFSHORE HOOK UP WORK FOR GSPC PLQP
PROJECT NAME : |
GSPC PLQP PROJECT OFFSHORE HOOK UP WORK FOR GSPC PLQP |
YEAR : |
2013 – 2014 |
LOCATION : |
K .G BASIN ,DEEN DAYAL FIELD. EAST COAST OF INDIA |
OPERATOR : |
M/S. GSPC LTD. |
CLIENT : |
M/S. LARSEN & TOUBRO LTD. |
VALUE (M. INR) : |
130 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
HOOK-UP, PRE-COMMISSIONING OF PROCESS CUM LIVING QUARTER PLATFORM – PLQP |
B-193 HOOK UP & COMMISSIONING WORK
PROJECT NAME : |
B-193 HOOK UP & COMMISSIONING WORK |
YEAR : |
2013 – 2014 |
LOCATION : |
MUMBAI HIGH BASSEIN FIELD,INDIA |
OPERATOR : |
M/S. ONGC LTD. |
CLIENT : |
M/S. SIME DARBY ENGINEERING SDN BHD. |
VALUE (M. INR) : |
1630 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
HOOK-UP WORKS ON PROCESS PLATFORM B-193 AP & AQ PLATFORMS. PRE-COMMISSIONING AND COMMISSIONING OF 103 SUB-SYSTEMS WHICH INCLUDES AGRU ( ACID REMOVAL UNIT) & AGDU(ACID DISPOSAL UNIT).
Piping-10,500 Inch. Dia.
Structural-320 MT
Cabling & Tubing-1, 55, 025 Mtrs |
MHN PP & LQ PROJECT
PROJECT NAME : |
MHN PP & LQ PROJECT |
YEAR : |
2011 – 2012 |
LOCATION : |
MUMBAI HIGH NORTH FIELD , INDIA |
OPERATOR : |
M/S. ONGC LTD. |
CLIENT : |
M/S. LARSEN & TOUBRO LTD |
VALUE (M. INR) : |
180 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
HOOK-UP AND PRE-COMMISSIONING WORKS OF MNP PROCESS, MLQ LIVING QUARTER, HP FLARE & LP FLARE PLATFORMS. |
MHNRD - II TOPSIDE MODIFICATION, ONSHORE FABRICATION & OFFSHORE HOOK UP CONSTRUCTION.
PROJECT NAME : |
MHNRD – II TOPSIDE MODIFICATION, ONSHORE FABRICATION & OFFSHORE HOOK UP CONSTRUCTION. |
YEAR : |
2010 – 2011 |
LOCATION : |
MUMBAI HIGH NORTH FIELD , INDIA |
OPERATOR : |
M/S. ONGC LTD. |
CLIENT : |
M/S. SWIBER OFFSHORE CONSTRUCTION LTD |
VALUE (M. INR) : |
165 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
ONSHORE FABRICATION, TOPSIDE MODIFICATION AND HOOK-UP WTH EXISTING FACILITIES ON WELL PLATFORMS WI-4, NB, N1, NV & N6.
ALSO FABRICATION OF RISER CLAMPS. |
N-18 COMPLETE DECK FABRICATION , PIPING, ARCHITECTURAL & E&I WORKS
PROJECT NAME : |
N-18 COMPLETE DECK FABRICATION, PIPING, ARCHITECTURAL & E&I WORKS |
YEAR : |
2010-2011 |
LOCATION : |
HAZIRA ,GUJRAT. INDIA |
OPERATOR : |
M/S. ONGC LTD. |
CLIENT : |
M/S. LARSEN & TOUBRO LTD |
VALUE (M. INR) : |
41.5 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
INSTALLATION OF WALL PANELS, TILES, INSULATION, INSTALLATION OF EQUIPMENTS, DUCTING ETC |
ARCHITECTURAL & HVAC WORK FOR LQ MODULE OF MHN PROJECT
PROJECT NAME : |
ARCHITECTURAL & HVAC WORK FOR LQ MODULE OF MHN PROJECT |
YEAR : |
2010-2011 |
LOCATION : |
HAZIRA, GUJRAT. INDIA |
OPERATOR : |
M/S. ONGC LTD. |
CLIENT : |
M/S. LARSEN & TOUBRO LTD |
VALUE (M. INR) : |
32.5 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
INSTALLATION OF HVAC EQUIPMENTS, PIPING, INSULATION, DUCTING WORKS AND ARCHITECTURAL WORKS FOR LQ MODULE. |
ARCHITECTURAL & HVAC WORK FOR GTG MODULE OF MHN PROJECT
PROJECT NAME : |
ARCHITECTURAL & HVAC WORK FOR GTG MODULE OF MHN PROJECT |
YEAR : |
2010-2011 |
LOCATION : |
HAZIRA, GUJRAT. INDIA |
OPERATOR : |
M/S. ONGC LTD. |
CLIENT : |
M/S. LARSEN & TOUBRO LTD |
VALUE (M. INR) : |
67.5 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
INSTALLATION OF HVAC EQUIPMENTS, PIPING, INSULATION, DUCTING WORKS AND ARCHITECTURAL WORKS FOR GTG MODULE. |
HOOK-UP WORK FOR HA-HB & IA PLATFORM – MOQ PROJECT
PROJECT NAME : |
HOOK-UP WORK FOR HA-HB & IA PLATFORM – MOQ PROJECT |
YEAR : |
2009-2010 |
LOCATION : |
AL SHAHEEN FIELD, DOHA OFFSHORE, QATAR. |
OPERATOR : |
MAERSK OIL QATAR |
CLIENT : |
M/S. LARSEN & TOUBRO LTD |
VALUE (M. INR) : |
210 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
HOOK-UP AND PRECOMMISSIONING OF WELL PLATFORMS HA, HB & IA |
BCP-A2 PROJECT
PROJECT NAME : |
BCP-A2 PROJECT |
YEAR : |
2008 |
LOCATION : |
MUMBAI HIGH BASSEIN FIELD, INDIA |
OPERATOR : |
M/S. ONGC LTD. |
CLIENT : |
SAMSUNG HEAVY ENGINEERING , KOREA |
VALUE (M. INR) : |
125 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
HOOK-UP AND PRECOMMISSIONING OF PROCESS PLATFORM BCP-A2 INCLUDING ASSISTANCE DURING COMMISSIONING AT BASSEIN FIELD. |
BCP-B2 PROJECT
PROJECT NAME : |
BCP-B2 PROJECT |
YEAR : |
2007 |
LOCATION : |
MUMBAI HIGH BASSEIN FIELD, INDIA |
OPERATOR : |
M/S. ONGC LTD. |
CLIENT : |
M/S. LARSEN & TOUBRO LTD. |
VALUE (M. INR) : |
70 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
HOOK-UP AND PRE-COMMISSIONING OF PROCESS PLATFORM BCP-B2 INCLUDING ASSISTANCE DURING COMMISSIONING AT BASSEIN FIELD |
PIPELINE REPLACEMENT PROJECT (PRP) PHASE - I, II & III
PROJECT NAME : |
PIPELINE REPLACEMENT PROJECT (PRP) PHASE – I, II & III |
YEAR : |
2006 -2007 |
LOCATION : |
MUMBAI HIGH BASSEIN FIELD, INDIA |
OPERATOR : |
M/S. ONGC LTD. |
CLIENT : |
M/S. LARSEN & TOUBRO LTD. |
VALUE (M. INR) : |
175 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
DECK EXTENSIONS, INSTALLATION OF LAUNCHER/RECEIVERS AND ASSOCIATED PIPING , E&I AND HOOK UP WITH EXISTING FACILITIES ON 34 WELL PLATFORMS AT MUMBAI HIGH NORTH, SOUTH AND HEERA & NEELAM FIELD. |
BDP PROJECT - BASSEIN DEVELOPMENT PROJECT
PROJECT NAME : |
BDP PROJECT – BASSEIN DEVELOPMENT PROJECT |
YEAR : |
2016 |
LOCATION : |
BASSEIN FIELD |
OPERATOR : |
M/S. ONGC LTD. |
CLIENT : |
M/S. LARSEN & TOUBRO LTD. |
VALUE (M. INR) : |
180 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
Hook up & Pre-commissioning of Process Platform BCP-A3, Living Quarter BLQ-3, Well Platform BH & related modification on BPA Complex (BPA, BCP-A, BCP –A2 & BLQ1). Replacement of Flare-Tip at MNF-1. |
LEWP-II (LIFE EXTENSION WELL PLATFORM PROJECT)
PROJECT NAME : |
LEWP-II (LIFE EXTENSION WELL PLATFORM PROJECT) |
YEAR : |
2016 |
LOCATION : |
MUMBAI HIGH NORTH & SOUTH FIELD |
OPERATOR : |
M/S. ONGC LTD. |
CLIENT : |
M/S. AFCONS |
VALUE (M. INR) : |
98.5 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
Onshore fabrication related to Topside Modification including Structural, Piping, Electrical, Architectural, Instrumentation, Fabrication of Handrails etc. of NU, NV & NT Platforms.
OFFSHORE TOPSIDE MODIFICATION, HOOK UP, PRE-COMMISSIONING & ASSISTANCE FOR COMMISSIONING OF THE WELLHEAD PLATFORMS (NU, NV & NT). |
LEWPP-I ( LIFE EXTENSION WELL PLATFORM PROJECT )
PROJECT NAME : |
LEWPP-I (LIFE EXTENSION WELL PLATFORM PROJECT) |
YEAR : |
2016 |
LOCATION : |
MUMBAI HIGH NORTH & SOUTH FIELD |
OPERATOR : |
M/S. ONGC LTD. |
CLIENT : |
M/S. AFCONS |
VALUE (M. INR) : |
761.1 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
REVAMPING OF 20 NOS WELL PLATFORM AT MUMBAI HIGH NORTH & SOUTH FIELD
ONSHORE FABRICATION (PIPING, STRUCTURAL), REPLACEMENT OF DAMAGED STRUCTURE, PIPING, INSTRUMENTATION, EQUIPMENTS, REVAMP/NEW TEST SEPARATOR, REPLACEMENT OF EXISTING HELIDECK WITH NEW ALUMINIUM HELIDECK PANELS, PLATFORM PAINTING FROM -1 TO HELIDECK LEVEL.
|
MP POORV KSHETRA VIDYUT VITARAN CO.LTD (MPPKVVCL)
PROJECT NAME : |
MP POORV KSHETRA VIDYUT VITARAN CO.LTD (MPPKVVCL) |
YEAR : |
2016 |
LOCATION : |
NARSINGPUR, MP, INDIA |
OPERATOR : |
M/S. MPPKVVCL (M. P POORV KSHETRA VITARAN CO.LTD.) |
CLIENT : |
M/S. MPPKVVCL (M. P POORV KSHETRA VITARAN CO.LTD.) |
VALUE (M. INR) : |
508.2 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
SUPPLY OF MATERIAL, SURVEY, INSTALLATION, TESTING & COMMISSIONING OF 11 KV FEEDERS UNDER FEEDER SEPARATION PROGRAMME FOR SEPARATION OF NON AGRICULTURAL AND AGRICULTURAL CONSUMERS IN RURAL AREA OF (O&M) DIVISION NARSINGPUR (LOT NO.15 R) OF NARSINGPUR DISTRICT OF MPPKVVCL JABALPUR (MP) AGAINST BALANCE PORTION OF ORIGINAL TERMINATED CONTRACT. |
FABRICATION OF TG BUILDING MODULE FOR BASSEIN DEVELOPMENT PROJECT)
PROJECT NAME : |
FABRICATION OF TG BUILDING MODULE FOR BASSEIN DEVELOPMENT PROJECT |
YEAR : |
2016 |
LOCATION : |
HAZIRA ,GUJRAT. INDIA |
OPERATOR : |
M/S. ONGC LTD |
CLIENT : |
M/S. LARSEN & TOUBRO LTD. |
VALUE (M. INR) : |
51.3 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
FABRICATION AND ERECTION OF STRUCTURAL MEMBERS, LEGPOTS, GRATINGS, FABRICATION OF PLATE GIRDER, ERECTION AND ALIGNMENT OF STATIC & ROTARY EQUIPMENTS, ASSEMBLY AND ERECTION OF COOLER STRUCTURE, ASSEMBLY AND ERECTION OF DUCTS, FABRICATION AND ERECTION OF PIPING & ASSOCIATED VALVES, FITTING, TESTING ETC |
TG BUILDING MODULE - BASSEIN DEVELOPMENT PROJECT
PROJECT NAME : |
TG BUILDING MODULE – BASSEIN DEVELOPMENT PROJECT |
YEAR : |
2016 |
LOCATION : |
HAZIRA ,GUJRAT. INDIA |
OPERATOR : |
M/S. ONGC LTD. |
CLIENT : |
M/S. LARSEN & TOUBRO LTD. |
VALUE (M. INR) : |
59.4 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
E&I, ARCHITECTURAL, HVAC & PIPING WORK AT TGBM PLATFORM & ARCHITECTURAL WORK OF BH WELL HEAD DECK OF BDP PROJECT. |
OFFSHORE HOOK-UP FOR PROCESS CUM LIVING QUARTER PLATFORM (PLQP) PROJECT (Amendment No.04)
PROJECT NAME : |
OFFSHORE HOOK-UP FOR PROCESS CUM LIVING QUARTER PLATFORM (PLQP) PROJECT (AMENDMENT NO.04) |
YEAR : |
2016 |
LOCATION : |
K .G BASIN ,DEEN DAYAL FIELD. EAST COAST OF INDIA |
OPERATOR : |
M/S. GSPC LTD. |
CLIENT : |
M/S. LARSEN & TOUBRO LTD. |
VALUE (M. INR) : |
339.3 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
REPLACEMENT OF EXISTING POTABLE WATER PIPING WHICH INCLUDES FABRICATION, INSTALLATION AND TESTING |
GSPC FLOWARMS AT DDW1 OFFSHORE PLATFORM
PROJECT NAME : |
GSPC FLOWARMS AT DDW1 OFFSHORE PLATFORM |
YEAR : |
2015 |
LOCATION : |
KG FIELD |
OPERATOR : |
M/S. GSPC LTD. |
CLIENT : |
M/S. GSPC LTD. |
VALUE (M. INR) : |
66.8 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
Fabrication, Transportation, Erection & Hook up of Flowarms at DDW-1 Offshore Platform for KG-OSN-2001/3 Block |
SBPDCL PROJECT
PROJECT NAME : |
SBPDCL PROJECT |
YEAR : |
2014 |
LOCATION : |
PATNA, BIHAR, INDIA |
OPERATOR : |
JOINT VENTURE WITH PRAVIN ELECTRICALS |
CLIENT : |
M/S. SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED. |
VALUE (M. INR) : |
2050 |
PROJECT STATUS : |
COMPLETED |
DESCRIPTION : |
DESIGN, SUPPLY OF EQUIPMENT AND MATERIAL, TRANSPORTATON & STORAGE, INSTALLATION/ERECTION INCLUDING ASSOCIATED CIVIL WORKS, TESTING COMMISSIONING INCLUDING PERFORMANCE TESTING OF ALL THE EQUIPMENTS SUPPLIED FOR STRENGTHENING, IMPROVEMENT AND AUGMENTATION OF DISTRIBUTION SYSTEM CAPACITY UNDER R-APDRP (PART B) SCHEME IN 9 TOWNS OF CENTRAL ELECTRIC SUPPLY AREA & 11 TOWNS OF MAGADH ELECTRIC SUPPLY AREA, PATNA AREA OF BIHAR ON TURNKEY BASIS |